Turbe Clinic for Medical Relief International (MERLIN)

Overviewteamupdatesworkspacecalendarfiles 
Wed, 2012-04-04 11:42

ARCHITECT’S FIELD REPORT
__________________________________________________________________
PROJECT: Turbe Clinic Medical ( Croix des Bouket)
PROJECT NUMBER: 9978
FIELD REPORT NUMBER: [10]
DATE: March 26-29
PRESENT: Architect, Contractor, Owner
__________________________________________________________________
WEATHER: []
COMPLETION: [98%]

__________________________________________________________________
WORK IN PROGRESS:
- water alimentation,instalation sink ,instalation shower.
- painting exterior wall, painting cabinet shelves.

this facede painting is complete

this facede painting is complete

water alimentation


__________________________________________________________________
PRESENT AT SITE:
- 1 capenter
- 1 Painters
- 2 plumbing
______________________________________________________________
DELIVERIES TO SITE: Date : 29/03/2012
-5 gals painting (9:00 AM)
-4 Timbers (10:00 AM)
_______________________________________
OBSERVATION :
- There's works on Site.

_______________________________________
Materials one Site:
-4 Timbers
________________________________________________________
INFORMATION OR ACTION REQUIRED:
- Romelus want to finish the work.

- We believe that all the work will be completed in 2 or 3 days, so it will be complete this Monday, April 2
_______________________________________
ATTACHEMENTS:
Romulus ,Ing Pierre Ulric.
_______________________________________
REPORT BY: Balan Rene