Tue, 2013-04-16 12:23

Construction of the 1rst classsroom building at ecole baptiste bon berger is DONE and COMPLETE.

Final walkthrough was performed on october 22nd of last year. Some minor items were noted to be fixed up and final report was sent out to the contractor on novmeber 22nd of that same year.
Punchlist report can be read by clicking on the following link:
http://openarchitecturenetwork.org/sites/default/files/active/44/Pele%20...

To the bigger issue of the contractor, the toilet building, security and next steps, a meeting with school director, Chedrik was held end of last year and was set up to go through, discuss and countersign all paperwork related to the finished classroom building. There was alot of frustration on the part of Chedrick with how this project, and this contractor has been handled. There's been some serious communication breakdowns between all parties. The school lay blame squarely with the contractor and made repeated reference to an "inside job". Also addressed in that meeting was the need for Chedrick to fully regain control of the site. The general preference around the table was for the contractor to walk, press the pause button on the project, let the site settle down, then regroup and blitz the toilet building in 4-6 weeks with another contract.

The contractor couldnt agree more with the proposed plan as he had already taken the decision internally to cease his involment in the project. Subsequently, a few meetings were held to walk through the mutual agreement to suspend / terminate the contract. We very simply explained per the terms of the contract the need and opportunity that does exist to withold payments from him to cover inflated cost of someone else carrying out the job. He had asked, understandably, for a few days to review the wording of the amicable agreement which he did, sent back with minor additions and signed.

Presently we're on the hunt for potential contractors to erect the toilet building. Concurrently, reviews to the drawing set are being made and hopefully by the end of the month, construction will resume.

 

Interested in hosting your competition on Worldchanging? Contact Us and tell us about your competition!

Website Design by Eben Design | Logo Design by Egg Hosting | Hosted by Amazon AWS | Problems with the site? Send email to tech /at/ worldchanging.com
©2012 Architecture for Humanity - all rights reserved except where otherwise indicated.
 

Find_us_on_facebook_badge.gif twitter-logo.jpg
Hosted on     Supported by