École Baptiste Bon Berger, Pele

Overviewteamupdatesworkspacecalendarfiles 
Mon, 2012-05-14 08:20

AfH is still reviewing the contractor’s recently submitted change orders, but the construction has continued pretty smoothly for the past two weeks on-site. This was mainly possible due to the outcome of the meeting held with the Committee formed by community members...meeting minutes to follow.

We resume with the block walls.
The first course of block for the Upper Floor being built. Notice the balcony slab with formwork at its edge in the midground.

More blocks laid up to window sill height.

Last week, they were about 60% up to door height throughtout the Upper Floor.

The next things to resolve are the windows/door design and the roof truss clip that will be embedded in the ringbeam.

 

Interested in hosting your competition on Worldchanging? Contact Us and tell us about your competition!

 

Who's online

There are currently 2 users and 697 guests online.

Online users

  • Kelo Kubu
  • soltani.landscape
Website Design by Eben Design | Logo Design by Egg Hosting | Hosted by Amazon AWS | Problems with the site? Send email to tech /at/ worldchanging.com
©2012 Architecture for Humanity - all rights reserved except where otherwise indicated.
 
Hosted on     Supported by