Oguaa Football for Hope Centre

Overviewteamupdatesworkspacecalendarfiles 
Tue, 2011-11-29 07:07

Plastering Complete
Changing room fit out 95% complete, plumbing installation 90% complete ( to be completed by 05th October)
3 sets of bamboo folding doors being fabricated, delayed delivery due to problems sourcing materials. Estimated delivery / installation date 10 October
Pitch lighting installation delayed, due for completion 05th October
Floor decking 90% complete ( requires sanding and varnishing, to be completed at end of project)
Septic tank 95% complete
Electrical installation 95% complete
Structural Bracing Installed, awaiting installation of frame clamps
Bamboo soffit 100% complete
External skin bamboo 95% complete
4 No change order requests from Play Soccer Ghana, to be issued for approval
Greenefileds container arrives in Ghana on 04th October, requested installation date 31st October
DF and Centre host to hold workshop for the painting of shipping containers / teaching spaces
EOT claim expected from main contractor requesting further extension
DF on vacation for 10 days from 05th October

 

Interested in hosting your competition on Worldchanging? Contact Us and tell us about your competition!

 

Who's online

There are currently 1 user and 712 guests online.

Online users

  • oliverkienzi
Website Design by Eben Design | Logo Design by Egg Hosting | Hosted by Amazon AWS | Problems with the site? Send email to tech /at/ worldchanging.com
©2012 Architecture for Humanity - all rights reserved except where otherwise indicated.
 
Hosted on     Supported by