Tue, 2014-01-14 09:20

Update as of 14th of January

• Construction progress has return to full pace after the holiday season.
• Currently concrete beams are close to completion and masonry walls ready to start after floor slab is complete.
• Representative from Opus (AoR) to visit the site the 17th of January for general review of the project execution and correct design interpretation.
• AfH is meeting with school representatives during the 13th of January week to coordinate general community engagement activities and general update of the construction progress.