February 22
Report:
•Last site visit: 20 February 2013 (Practical Completion Inspection)
•Municipal sewer completion is delayed indefinitely and therefore bulk sanitation and water systems to centre remain unconnected. The consultancy team was unable to test and approve connections therefore handover could not occur. The Contractor has met all other requirements for Practical Completion and thus the Architect of Record and Design fellow will issue Practical Completion certificate back dated to 20 February 2013, once bulk services to the centre are finalized. We are of the opinion that the Contractor can no longer be penalized for works beyond his responsibility.
•Copy of snag-list for specific in-depth items to be posted on the Open Architecture Network.
•Outstanding general work: Toilet seat covers to be replaced. Handrails to be secured. Pole with hook to be provided for opening of clerestory window.
•FFH Building plaque: Design fellow awaits list of contributors/ donors from Centre Host. Draft plaque to be issued to FIFA by 27 February. All other signage drafts to be circulated at the same time.
•The Quantity Surveyor has confirmed additional funds within the budget which will be allocated for a perimeter fence around the centre. It has become priority that the property is secured. Design fellow/Quantity Surveyor/ Contractor are working together to acquire suitable quotations that meet the budget. Specifications are to be finalized by 26 February 2013 for ordering of materials.
Current Challenges:
•Payment to Contractor: payments made to contractor currently equal 1/3 of contract value with payment certificate #3 pending will roughly equate to 2/3 when made. We are currently behind the payment schedule and thus will require, where possible payments be expedited by AfH to catch up as we begin to wrap up FFH Mokopane project. Design fellow is to coordinate with program manager for assistance in fast tracking process. Program manager is to correspond with Architecture for Humanity headquarters in an effort to fast track current payment. Design fellow expects next payment invoice (certificate #4) from Quantity Surveyor within the next 2 weeks.
Center Host (DCCV):
•Centre Host to issue draft program for Opening Ceremony. Design fellow will circulate to relevant parties once obtained. Ceremony dignitaries to include: Member in the Executive Council for Sports, South African Football Association, local and district mayor’s office and local soccer celebrities.
Anticipated Critical Steps:
•Payment Certificate #3 – payment made to Matakanye Construction CC
•Lightpoles and solar lighting installation 25 February – 1 March 2013
•Application for Building Occupancy Certificate pending Practical Completion. To be obtained before 8 March 2013
•Centre Opening 8 March 2013
February 15
Building:
•Date of site handover: 29 August 2012
•Date of Practical Completion: Wednesday 20 February 2013
•Estimated Date of Works Completion: 27 February 2013. Defects Liability Period (90 calendar days) begins at Works Completion.
•Date of Final Completion: 28 May 2013 (Inspection after lapse of Defects Liability Period)
Subbase:
•Date of commencement: 14 November 2012
•Date of estimated Final Completion: 25 January 2013 - Works completed. Final Completion certificate pending Greenfields sign-off. Estimated by 1 February 2013
Greenfields Installation:
•Date of install: 25 January – 4 February 2013.Completed
Yingli/ Phaesun Installation
•Date of install: 25 Feb – 1 March 2013
Opening Event:
•Scheduled Date: 8 March 2013
•Last site visit: 13 February 2013
•Tiling complete. Electricity supply and works to building complete. Joinery complete. Concrete footings for light poles complete. Painting complete. Pergola shading in process.
Anticipated Critical Steps:
•Municipal sewer construction. 21 January – 20 February 2013
•Practical Completion inspection 20 February 2013
•Lightpoles and solar lighting installation 25 February – 1 March 2013
•Application for Building Occupancy Certificate pending Practical Completion. To be obtained before 8 March 2013
February 8
•Practical Completion date: POSTPONED (due to availability of all consultants) Design fellow to advise next suitable date upon input from consultancy team. Fellow to discuss the merits of Practical Completion coinciding with the completion of the municipal sewer (20 February 2013) with AfH program manager.
•In this scenario: Estimated Works Completion: 27 February 2013. Defects Liability Period (90 calendar days) begins at Works Completion.
•In this scenario: Estimated Final Completion: 28 May 2013 (Inspection after lapse of Defects Liability Period)
•Outstanding work: tiling to wet areas: Kitchen and bathroom floors. External pergola shading to be fixed to detail. Final cleaning of brick walls. External benching to be fitted outside multi-purpose space. Concrete footings for light poles to be completed 8 Feb. Steel gates to doors to be complete for Works Completion. FFH Building plaque to be ready for Works Completion. General grading/clean up of premises.
•‘Payment Certificate #3 has been issued by the QS. Design fellow to forward to AfH for processing and payout. QSto begin finalizing Final Account after Practical Completion.
February 1
•FFH Pitch Installation currently underway until 3 Feb.
•Practical Completion date: 11 February 2013
•Estimated Works Completion: 20 February 2013 (date given by the municipality for completion of sewer) Defects Liability Period (90 calendar days) begins at works completion.
•Estimated Final Completion: 21 May 2013 (Inspection after lapse of Defects Liability Period)
•Opening Ceremony: 8 March 2013
January 18
•Next Site Meeting 09: 30 January
•Estimated Practical Completion date: 8 February 2013 (tentative based on outfall sewer and soccer pitch installation) To be finalized by 23 Jan
•Estimated Final completion: 11 March 2013
•Opening Ceremony: 8 March 2013 (provisional pending input from FIFA)
Windows/ Doors - completed.
Ceiling - completed.
Roof - completed.
Paint - 85% completion – excluding containers
Electricity - completed.
Plumbing - completed.
Sub-base - 85% completion
Joinery - 85% completion
Tiling- 20% completion
January 11
•Next Site Meeting 08: 16 January
Construction Report:
Windows/ Doors - completed.
Ceiling - 85% completion
Roof - completed.
Paint - 65% completion
Electricity - 85% completion
Plumbing - 65% completion
Sub-base - 65% completion
Anticipated Critical Steps:
•Sub base finalization and completion of pitch installation.
October 19
• Brickwork currently to window sill height.
• Steel frame doors and windows are being put in place.
• Variation Order #2: Awaiting comments/ approval.
• Greenfields issued 19 Oct: Revised technical drawing set including new
specifications and revised BOQ for pitch sub-base. Design fellow to
discuss with consultants and Contractor.
• Yingli/Phaesun reports sub-base lighting goods are ready for shipment.
Design fellow to liase with Centre Host for verification of shipping
details.
• Revision of Practical Completion pending approval by
streetfootballworld/FIFA.
October 12
• Masonry: 28 SEPT – 18 OCT Delayed by 2 Weeks. To commence 15 Oct.
• Next Site Meeting 04: 24 OCT.
• Payment Certificate 01: Expected by 16 Oct.
• Practical Completion: 21 Dec 2012 – Delayed by 1 week (to be revised
with program manager) To be partial completion of main building works.
Pitch installation to be completed in February 2013.
• Foundation concrete has been cast and foundation walls erected. Fill
under surface bed has been compacted and samples sent to laboratory for
assessment. Engineer to give approval upon verification of test results.
• Storm water drain is nearly complete.
• Community meeting held 6 October on site was successful. Centre Host
George Mamabolo facilitated meeting along with ward councilors. 15
labourers were chosen for general works on site.
• Ms.Ruth Madidimalo has been selected as the Community Liaison Officer.
October 5
• Site Meeting 03 to be held Wednesday 10 October on site.
• Foundations trenches have been dug and tested for compaction. Contractor
awaiting results for Engineer’s approval.
• Variation Order #2: Delayed. Contractor set to claim 5 additional
working days due to blasting of boulders for foundations platform.
Practical Completion date to be revised as it will run into Builder’s
Holiday (14 December 2012 – 7 January 2013)
• Community meeting to discuss labour matters including electing of
Community Liaison Officer to be held by 5 October. Centre Host to
provide feedback.
• Construction Guarantee has been obtained and submitted to Architecture
for Humanity - 3 October.
September 28
• Earthworks + Foundations: 13 – 25 SEPT: Delayed due to factors outline
in report.
• Next Site Meeting 03: 10 OCT.
• Contractor has placed the platform for building’s foundations incorrectly. The implications being that 1). Either the platform has to be extended to building’s correct position or 2). The building and pitch positions will have to be moved. Design fellow assisted by the Engineer has taken the decision that option 2 is the ‘lesser evil’ due to the following factors: 1). Sporadic sub-terrainian rock outcrops will require blasting – which will lead to added costs to the project. 2). The project will experience at least a week’s delay for excavations, new fill compaction and testing. A contract instruction has been given for the Contractor to implement these changes based on a survey by the Land Surveyor, approved by the Engineer. The Land Surveyor has pegged the final positions of the building and pitch.
• Variation Order #2 has been received from the QS. Design fellow to
forward to program and construction manager for administrative
coordination.
• Payment Certificate #1 has not been finalized as the QS awaits
quantities for the platform, and soil compaction test results to render
his evaluation.
• Greenfields provides schedule of dates for sub-base material delivery and pitch installation. Proposed dates are beyond date for Practical Completion and will need urgent review.
• Outfall sewer design by the Municipality remains pending.
September 14
• Earthworks + Foundations: 13 – 25 SEPT
• Technical Site Meeting 02: 26 SEPT.
• Contractor is finalizing general grading and levels for foundations of
building and pitch.
• Design fellow and QS still await quotation from Contractor for blasting
of rocks for timeous processing of Variation Order #2.
• FFH design has been approved by the local authority. 1x set of drawings
to be kept in site office for the duration of construction.
• FFH design has been approved by the local authority. 1x set of drawings
to be kept in site office for the duration of construction.
September 7
• Site Meeting 01: 12TH SEPT. at 10h00 on site.
• Site Clearing and Grading: 3RD – 14TH SEPT.
• Payment Certificate 01: To be submitted the 27th SEPT.
• Heritage Day Holiday: 24th SEPT.
- The contractor continues with general site clearance as per works programme.
- The contractor has indicated the extent and size of hard rock boulders found on site exceeds the measured amount in the Bill. These boulders cannot be dug up and therefore blasting is required, this has been confirmed by the civil consultant.
- Greenfields has been notified of project ‘go-ahead’ on site, design fellow is awaiting further input for delivery of sub-base containers.
- Phaesun has been notified of project ‘go-ahead’ on site, design fellow is awaiting further input for delivery of solar components and light poles.
August 31
- Site Hand-over meeting was held 29TH AUG. at the offices of the centre host SARCS in Mokopane. All consultants were present in addition to the contractor, centre host and Ward 29 councilors.
- The contractor has works and public liability insurances in place and has taken possession of the site 29TH SEPT works to begin Monday 3RD SEPT.
August 24
• Site Handover Meeting: 29th AUG.
• Sod Turning Ceremony: 31st AUG.
• Practical Completion: 14th DEC.
- Pre-construction meeting was held on the 24th with Brandon Dreyer of streetfootballworld in attendance. The meeting was a success with all delegates positive.
- 31st of August, 9h00 – is the date and time set for sod turning. Ceremony to involve municipal officials, community and councillors, centre host and local media.
August 17
- Signed Contract Submission to AfH: 20th AUG. (Previously 17th) Delayed due to conflicts of schedules: Aor, QS and Contractor.
- FFH Building Contract Approval – AfH: 22nd AUG.
- Pre-Construction Meeting: 24th AUG.
- Site Mobilisation: 22nd – 29th AUG.
- Site Handover: 29th AUG.
- Practical Completion: 14th DEC.
- Sod Turning Ceremony: Tentatively set for the 29th of August. To be confirmed
*Note – current schedule dates have been revised with program manager and reflect ‘best outcome’ scenario provided there are no unforeseen delays.
- AfH has issued the Letter of Intent (14 August) for the appointment of Matakanye Construction CC.
- Matakanye have confirmed the 15 week construction period and Site Hand-over and Practical Completion dates as noted above.
- Design Fellow has met with the civil consultant to discuss sewerage installation for FFH site in light of the possibility that the outfall sewer will not be constructed in co-ordination. This matter theoretically should not delay the progress of FFH construction program. (subject to outfall sewer line connection occurring within the set construction period) - Design Fellow has met with the civil consultant to discuss sewerage installation for FFH site in light of the possibility that the outfall sewer will not be constructed in co-ordination. This matter theoretically should not delay the progress of FFH construction program. (subject to outfall sewer line connection occurring within the set construction period)
- Brandon Dreyer (sfw) due for site visit 24 August to tie in with Pre-Construction Meeting. Venue and time to be confirmed.
August 10
- Tender Report APPROVED by sfw/FIFA: 10th AUG
- Design Fellow is waiting for the appointment of a contractor in order to advise Phaesun dates for delivery of solar lighting components to site in co-ordination with construction program. To advise within the next 3 weeks. ONGOING
August 03
- Tender Report Submitted to sfw/FIFA: 1ST AUG
- Tender Report Submitted to AfH: 1ST AUG
- Tender Report Approval: 8th AUG
- AfH has approved civil/struct agreement with DCE Consultants.
- AfH has made payment to ADI Consulting (geotech)
- Design Fellow has learned that the Manager of Technical Services is no longer in the employ of the Municipality. The manager was steering the process for construction of the outfall sewer to service the Football for Hope site. It is unclear at this time who will be taking over. Implications to the project program require clarity. EXPECTING SIGNIFICANT DELAYS
JULY 13th
- DF liasing with QS and Program Manager for value engineering for tender price negotiations with Matakanye Construction. Prices currently above FIFA budget.
- Vat exemption is being discussed for further reduction in pricing.
Anticipated critical steps:
- Progress has been made with Municipality for facilitation of construction of outfall sewer line. DF to engage Program Manager re recommendations to be made by AfH for appointment of Civil consultant by Municipality. This item is now on the critical path.
- Approval of consultants contracts by AfH. Urgent attention will be required.
Current Challenges:
- Bidders and QS have expressed frustration of rigid budget which makes little account of local construction conditions. DF finds it increasingly difficult to find a balance between a good design with all STATUTORY requirements and the bottom line cost in preparation of recommended contract sum.
FEB 03
• DF in ongoing process to engage consultants re finalisation of contracts and design for preparation of DD package.
• Geo-technical report quotation has been submitted by WSM Leshika Consulting Engineers and is currently being negotiated.
• DF has urged the CH to confirm VAT exemption for construction as soon as possible..
FEB 10
• DF finalising two separate Structural Engineer contracts with Program Manager for KFD Wilkinson, who will provide PRO BONO 'Design/Engineer of Record' services from Cape Town and VW Civils/Structural who will provide Site Supervision services at a fee.
• DF to search for a new QS consultant, as YMCAQS becoming increasingly unrealiable and as of yet have not provided any cost insight for the design.
Mogalakwena Municipality: Feedback on provision of utilities budget still outstanding. Expect correspondence by the end of February latest.
• DF still to liase with SARCS re securing VAT exemption for construction from SARS. Process ongoing and currently undefined.
• DF relocation has been postponed from the 15th of February to the 1st of March, as first available date for car transport by train is the 29th of February. DF will use the time to finalise consultants agreements and DD package submission.
FEB 17
• Geo-technical soil analysis report.
• DF working on appointments of Engineers and Cost Consultant.
• DF finalising geo-technical consultant Agreement with ADI Consulting .
• DF finalising two separate Structural Engineer contracts with Program Manager for KFD Wilkinson, who will provide PRO BONO 'Design/Engineer of Record' services from Cape Town and VW Civils/Structural who will provide Site Supervision services at a fee. ONGOING. Drawings to be prepared by Design Engineer for DD submission.
• KC Maiwashe Associates QS have been approached for costing services. Terms of agreement an ongoing process.
• Quote from VW Civil Services CC for site supervision services currently under review. Contract to be finalised upon Program Manager/DF approval
FEB 24
• DF finalising two separate Structural Engineer contracts with Program Manager for KFD Wilkinson, who will provide PRO BONO 'Design/Engineer of Record' services from Cape Town and VW Civils/Structural who will provide Site Supervision services at a fee.
• DF still to liase with SARCS re securing VAT exemption for construction from SARS. Process ongoing and currently undefined.
• DF relocation has been postponed from the 15th of February to the 1st of March, as first available date for car transport by train is the 29th of February. DF will use the time to finalise consultants agreements and DD package submission.
JAN 13
• Schematic Design Package submitted to sfw, AfH, CH 13th of January 2012. Approval with comments expected 20th of January.
• DF has confirmed QS to provide pro-bono services, to submit signed QS/Project Lead Agreement within the week for urgent approval.
• DF in preparation for site relocation in 2-3 weeks.
JAN 20
• DF has responded to comments re SD package submission from sfw and is awaiting final resolution. Tentatively moving forward with DD.
• CH and DF will have to wait until the end of Feb. 2012 to find out if the Municipality will have the funds necessary for the implementation of services to site. In the interim DF to liase with council officials re service reticulation planning.
• Municipality confirms there are no geo-technical or environmental impact assessment (EIA) reports for the property. DF to engage consultant immediately for soil analysis report and liase with Environmental Department re necessity of EIA report.
• DF in talks with potential structural engineers and is reviewing proposals.
JAN 27
• SCHEMATIC DESIGN PACKAGE approved on 25TH JANUARY 2012 with comments on the number of corners on the building and overall height.
• CH has okayed the schematic design and will aid in liasing with municipality for requirements for local authority submission.
• KFD Wilkinson Consulting Engineers have been approached for structural design and documentation services, Agreement docs to be prepared.
• DF on trail for geo-technical consultant, the matter is ongoing.
• AoR Agreement has been received and forwarded to MEG Architects along with Schematic document and Schedule.
• DF preparing for site relocation. Date is set as the 15th of February.
• OAN Page has been updated.
• Expected date of Schematic Design submission to sfw/FIFA December 15.
• Brief delays have been incurred to the project due to the need for DF to travel to site to meet with the municipality regarding services to be provided to the site.
NOV 04
• Design Brief revised and re submitted to sfw October 28th, 2011. Approval feedback needed by the 4th November, 2011.
• DF finalising AoR with MEG Architects of Polokwane, who have agreed to provide their services pro-bono.
• AoR to assist DF in canvassing for a QS and structural engineer.
• DF to send land surveyor quotation to San Francisco for approval within the new week.
NOV 18
• DF in ongoing process to secure consultants for FFH Centre project.
• Louis Nel Land Surveyor contract has been sent to San Francisco (14th Nov) feedback has been received awaiting LS to forward signed Fifa A & E Subcontractors Annex.
• In communication with YM Cassim and Associates Quantity Surveyors from Mokopane and Maiwashe Quantity Surveyors from Polokwane.
• DF to visit site (21st -22nd Nov) to hold meeting with Mogalakwena Municipality to co-ordinate installation of water, electricity and sewerage services to site with project schedule.
• DF to meet with Centre Host to discuss progress of Schematic Design
• DF to meet potential quantity surveyors in Mokopane and canvass for Structural Engineer.
NOV 25
• DF has returned from 2nd site visit
• Meeting held with Mogalakwena Local Municipality and Centre Host SARCS (21.nov.2011) to present site development plan and discuss municipality obligations as prescribed in the MoA in order to co-ordinate delivery of bulk services with the project schedule.
• DF to forward schematic drawings 'as they come' to co-ordinate with council officials for the installation of services.
• Meeting was fruitful as DF was able to gain clarity regarding municipality expectations for the site and general protocol. DF has gained contact details for heads of Planning, Electrical, Stormwater and Drainage departments and established a liason official within the council for general communication.
• DF and Centre Host met (22.nov.2011) to discuss the on going process of schematic design. CH has expressed satisfaction with the general progress of the project.
• DF met with local quantity surveyor YM Cassim & Associates. Company has expressed keen interest to do pro-bono work as they desire to give back to their community.
• QS and AoR Pro-Bono Agreements are being finalised and may be reviewed during DF San Francisco trip 5th - 9th December.
• Land Surveyor has promised to complete survey next week. The finalisation of these works has become critical to the planning and costing of the overall project at schematic level.
• Schematic Design submission, December 9th.
OCT 07
• The Project Schedule is being finalised. To be issued 6 October.
• Site Visit Report to be finalised by the end of the week.
• Design Brief and Concept Design Submission scheduled for 14 Oct 2011
• Contacted Louis Pieterse Head Building Control Officer for local municipality for leads on land surveyors in the area.
• A Louis Nel is the only local surveyor recommended
OCT14
• Project Schedule has been revised with sfw input. - Brandon Dreyer.
• Design Brief and Concept Design Submission is now 21st Oct 2011.
• Two independent Land Surveyors have been engaged (Louis Nel, Mokopane & R. Maesela, Polokwane). Awaiting queries. Consultants to provide quotations thereafter.
OCT 21
• Project Schedule has been updated.
• Concept Design/ Design Brief submission remains the 24th October 2011.
sfw Centre Host Workshop in Cape Town 23 - 27 Oct. 2011. DF to meet with SARCS Centre Host to discuss concept design.
• Quotation from Maesela Professional Land Surveyor Inc. has come in quite expensive. DF anticipating second quotation, from Louis Nel Professional Land Surveyor to come in cheaper as the consultant is based in Mokopane and has already completed some survey work on the property.
• DF to finalize relationship with AoR within the next two weeks.
OCT 29
• Design Brief Package submitted 24th October to AFH San Francisco. DF awaiting response by 27th Oct.
• DF and Centre Host representative George Mamabolo met on 25th Oct. Discussion centered on • Design Brief and Concept Design.
• Centre Host issued DF a final copy of the SARCS Strategic Plan for the FFH centre. A copy was issued to sfw also. DF anticipates minor revisions to be incorporated into brief, which will be circulated accordingly.
• Centre Host has endorsed conceptual site layout with minor alterations. DF to investigate.
• Louis Nel Professional Land Surveyor quotation has been accepted, DF waiting to receive Bank Information Form and W8-BEN to forward to San Francisco.
There is a need to confirm the structure and timeline of the commitment of the local municipality to provide services to the site. (water, electricity, sewerage)
SEPT 02
• DF has contacted local architects and has received company profiles.
• DF following up with phone calls.
• DF researching and compiling a list of other building consultants.
SEPT 09
• Design Fellows, Mark Warren and Themba Mekwa, in Mokopane for re-initiation site visit.
• Reviewing existing Design Brief with center host, Design Workshop,
• Meeting with local consultants and building authorities, and assessing building site.
SEPT 15
• Design Fellows, Mark Warren and Themba Mekwa, completed initiation site visit.
• DF to prepare schedule




March 8
Schedule:
•Building:
Date of site handover: 29 August 2012
Date of Practical Completion: Wednesday 20 February 2013
Date of Works Completion: 27 February 2013. Defects Liability Period (90 calendar days) begins at Works Completion.
•Date of Final Completion: 28 May 2013 (Inspection after lapse of Defects Liability Period)
•Subbase:
Date of commencement: 14 November 2012
Date of Final Completion: 25 January 2013
•Greenfields Installation:
Date of install: Completed 1 February 2013
Yingli/ Phaesun Installation
Date of install: Completed. 25 – 27 Feb 2013
Opening Event:
Scheduled Date: Occurred on 8 March 2013
•Design Fellow contract expires Friday 15 March 2013
•The Opening Ceremony hosted by Red Cross was a success! Representatives of local and provincial government were present as well as streetfootballworld and FIFA. The event was in two parts, commencing at the Municipal Chamber and then moving onto the Football for Hope premises. A key note address was given by Member of the Executive Council (MEC) Ms. Dipuo Letsatsi-Duba for the Department of Sport, Arts and Culture on behalf of the premier of Limpopo Province. In honouring International Womens Day, the first official match played on the Football for Hope pitch was between 2 girls under 16 soccer teams. The community showed their support with attendance even though the day was hindered by the presence of heavy rains in the morning. Food and beverages were served to all to compliment performances from local entertainers.
Report:
•Last site visit: 6 - 8 March 2013
•Connection to Municipal sewer line was made on 7 March 2013. Line was tested and is operational. The Municipality will continue to monitor functionality as the system will be in full use.
•Payment Certificate 3: Contractor has confirmed receipt of payment. Payment Certificate 4 currently in process of approval by Architecture for Humanity. This will be the penultimate payment to the Final Account.
•Outstanding works for Final Completion: Steel gates to doors have been condemned as the manufacturing was not to detail specification. Amendments are currently underway and should be complete by Friday 15 March 2013.
•Building signage: External signage to be returned to manufacturer, due to limited time temporary signs have been created for the Opening. Final signage to be completed by Friday 15 March 2013.
•Fencing and parking area were completed in the run up to the Opening. Design fellow secured a late donation from the Municipality for 20 indigenous trees and ground cover planting to guard against soil erosion. This brings to total 28 trees currently on site.
Yingli/ Phaesun:
•Status of work: Completed. Date of Installation: 25 – 27 February 2013
•Final Completion: 6 x antennas were missing and therefore each solar panel cannot be programmed individually. Design fellow is coordinating with Francis Hillman of Phaesun and Trevor Wheeler of SolarSun for the delivery of antennas and installation/ programming on site. Final Completion will be confirmed once materials are in the country. In the meantime, solar light panels are operational. Maiden ‘switch on’ was the evening of 27 February 2013. Centre Host is aware of status. Manuals and master remote were handed to the Centre Host 1 March. Certificate of Acceptance was signed by the Centre Host at this time.