JUNE 01
• Contract signed by contractor
• Sent to SF for counter signing

JUNE 08
• Site hand-over date (pending contract documents and advance payment)
• Contractor has outlined his preference to start ASAP due to
deteriorating roads increases materials transport cost and potential
delays
• Contractor Signed Contract submitted to AFH for Approval the 5th June
• Obtained Performance Bond, Guarantee, banking details, tax form
• Meeting insurance company Monday 11th
• Solar Panel Equipment being shipped from Germany the week of 11th of June

JUNE 18
• Site hand-over date (pending contract documents and advance payment)
• Contractor has outlined his preference to start ASAP due to
deteriorating roads increases materials transport cost and potential
delays
• Design fellow continuing to liaise with Contractor, Nominated Subcontractors and all relevant parties, in addition to the implementation of project administration.

 

Interested in hosting your competition on Worldchanging? Contact Us and tell us about your competition!

Website Design by Eben Design | Logo Design by Egg Hosting | Hosted by Amazon AWS | Problems with the site? Send email to tech /at/ worldchanging.com
©2012 Architecture for Humanity - all rights reserved except where otherwise indicated.
 

Find_us_on_facebook_badge.gif twitter-logo.jpg
Hosted on     Supported by