Collège Cœur Immaculé de Marie

Overviewteamupdatesworkspacecalendarfiles 
Tue, 2013-05-21 12:39

REPORT #21

PROJECT: CIM
PROJECT NUMBER: 10020
DATE: 2013-05-14
WEATHER: Sunny


SUMMARY:

Work was still slow this week because materials weren’t delivered to the site. Nonetheless, the last bit of slab was poured on the first floor, and blocks were laid on the remaining interior wall, up to the intermediate chainage. Crepissaging on the cantilevers is nearly finished, while formwork for the interior shear walls is being installed.

YCF also poured a small portion of an interior column with masonite backed formwork. The resulting concrete was generally of good quality; however, technical problems were still present during the pour. A concrete vibrator of inadequate power was used, and several blocks in the wall were broken during the process.


ATTENDEES:

Sven Kalim (Architecture for Humanity) (AFH)
Julien Jackson (AFH)
Taïna Mayard YCF Group, S.A. (YCF)
Lirode Deplat (YCF)
Lizzie Blaisdell (Degenkolb) (DK)


CONSTRUCTION PROGRESS:

-Crepissaging of cantilevers is nearly complete; currently crepissaging cantilever @ grid line 1
-Remainder of first floor slab poured (from grid line 2.5 to grid line 5.5)
-Poured up to (4) blocks of the middle column on grid line 10
-Laid block @ grid line 4 up to height of intermediate chainage
-Installed rebar grid for shear wall @ grid line 4, up to height of intermediate chainage
-Formwork for shear wall @ grid line 7 being installed


CONSTRUCTION NOTES:

-A portion of a column (4 blocks in height) was poured on grid line 10, using masonite. The results were much better than previously seen (less seepage of sauce; nicer concrete finish). However, some chronic problems were still evident. Concrete still did not reach all areas of the staggered block, leaving voids along the interface between block and concrete. This may have been a consequence of using a weaker, battery-powered, vibrator (this vibrator should not have been used for any concrete pours, as was explicitly stated in a previous meeting minutes). Also, several of the blocks broke in the areas where the staggered block is floating. AFH to address this problem prior to pouring the next lift.
-Because the first floor slab was not poured to the finished quality requested by AFH, YCF will polish the first floor slab after work on that floor is complete; a polishing test must be done by YCF prior to implementation on the building
-It was observed that one row of shoring for the first floor decking was removed in the middle room on the ground floor; YCF to replace shoring
-There has been some confusion about the (3) day curing time of concrete. Previously, YCF workers counted the day of a pour as one full day, and would remove formwork before a full (3) days had been reached. For clarity, formwork on newly poured concrete should be removed after at least 72 hours, from when the pour began
-The battery operated vibrator should not be used at any time while pouring concrete at CIM; for the best, the vibrator should be removed from the site


ADDITIONAL NOTES:

-AFH will not be working Friday, May 17, 2013 because of a Haitian holiday

(photo below)


(above) the results of the masonite backed formwork pour

 

Interested in hosting your competition on Worldchanging? Contact Us and tell us about your competition!

Website Design by Eben Design | Logo Design by Egg Hosting | Hosted by Amazon AWS | Problems with the site? Send email to tech /at/ worldchanging.com
©2012 Architecture for Humanity - all rights reserved except where otherwise indicated.
 

Find_us_on_facebook_badge.gif twitter-logo.jpg
Hosted on     Supported by