Collège Cœur Immaculé de Marie

Overviewteamupdatesworkspacecalendarfiles 
Tue, 2013-05-14 07:33

REPORT #20

PROJECT: CIM
PROJECT NUMBER: 10020
DATE: 2013-05-07
WEATHER: Sunny


SUMMARY:

Work was slow this week because materials weren’t delivered to the site. Crepissaging on the ground floor continued on the cantilevers, and several corrections were made to the reinforcing bars (rebar) on the first floor.


ATTENDEES:

Sven Kalim (Architecture for Humanity) (AFH)
Julien Jackson (AFH)
Taïna Mayard (YCF Group, S.A.) (YCF)
Lirode Deplat (YCF)
Lizzie Blaisdell (Degenkolb) (DK)


CONSTRUCTION PROGRESS:

-work has been slow last week because cement has not been delivered to the site
-Crepissaging cantilevers @ grid lines 1 through 10
-Rebar hooks in shear walls @ grid lines 2 & 3, and 5 & 6 corrected


CONSTRUCTION NOTES:

-Floor slab will slope to 12cm @ grid line 4; i.e., grid line 5.5 to grid line 4 (~13cm to 12cm), and grid line 2.5 to grid line 4 (~15cm to 12cm)
-Rebar cages in the small columns and intermediate chainage are fabricated to an appropriate size (approx. 14cm by 14cm); either block is not in the correct position (i.e., on axis with the rebar cages), or rebar cages are not correctly positioned – verify in field; the details provided by AFH for the end columns will be used on the first floor; Lizzie (DK) to provide information about maximum allowable coverage? YCF to check if all column rebar cages are plumb
-Crepissage on the cantilevers and beams chamfer must be 45° (3cm vertical; 3cm horizontal)
-It is good construction practice to apply the same rebar hook detail used in the shear walls to splice rebar from block walls into columns
-It is good construction practice to stagger the splicing of rebars
-Floor slabs must be protected during ongoing construction; plywood must be placed on the slab when storing materials, and/or when blocks need to sit on the slab to work


ADDITIONAL NOTES:

-AFH will not be working Friday, May 17, 2013 because of a Haitian holiday

(photos below)

   
(above) rebar ties were correctly fabricated -- 14cm by 14cm; see report #19


(above) another column detail will need to be used on the first floor to have the proper concrete coverage on the rebar

 

Interested in hosting your competition on Worldchanging? Contact Us and tell us about your competition!

Website Design by Eben Design | Logo Design by Egg Hosting | Hosted by Amazon AWS | Problems with the site? Send email to tech /at/ worldchanging.com
©2012 Architecture for Humanity - all rights reserved except where otherwise indicated.
 

Find_us_on_facebook_badge.gif twitter-logo.jpg
Hosted on     Supported by